Sr.
No. |
Name of the Project
and Location
|
Project
Cost
(INR Million)
|
Remark |
| 01 |
Construction
of Soap Plant at Barotiwala, Himachal Pradesh for
M/s. Hindustan Unilever Ltd.
Consultant: M/s. Kværner Powergas (India) Pvt. Ltd.
|
197.00
+
130.00* |
Completed before time in 14 months with earlycompletion bonus
YEAR: 2003-04. |
| 02 |
Construction
of Palm Oil Refinery at Kandla, Gujrat for
M/s. Cargill India Pvt. Ltd.
Consultant: M/s. Kværner Powergas (India) Pvt. Ltd.
|
106.00
+
75.00*
|
Completed in time in 8 months.
YEAR:2003-04. |
| 03 |
Construction of Process Catalyst Plant at Taloja for
M/s. Johnson Matthey Chemicals Pvt. Ltd.
Consultant: M/s. Kværner Powergas (India) Pvt. Ltd.
|
65.00 |
Completed in time in 6 months.
YEAR:2003-04.6 |
| 04 |
Construction of Vegetable Oil Refinery at Paradip, Orissa for
M/s. Cargill India Pvt. Ltd.
Consultant: M/s. Kværner Powergas (I) Ltd, Pune. |
73.00
+
25.00*
|
Completed in time in 6 months.
YEAR:2003-04.
|
| 05 |
Adhesive and Water Based Latex Polymers Plant at Taloja, Navi Mumbai for
M/s. Rohm and Haas (India) Pvt. Ltd.
Consultant: M/s. Jacobs H & G Pvt. Ltd.
|
115.00 |
Completed
in time in 15 months.
Safety excellence award from "Construction
Users Round Table (CURT) in United State of America
Excellence in Construction from "Association of Consulting Civil Engineers (India)"
YEAR:2002-03. |
| 06 |
Construction
of Soap Plant at Bhuj, Gujarat for
M/s. Aquagel Chemicals Pvt. Ltd.
Consultant: M/s. Kværner Powergas India Ltd.
|
62 .00
+
29.00*
|
Completed in time in 6 months.
YEAR:2002-03. |
| 07 |
Construction of Coconut Oil extraction Plant, Pondichery for
M/s. Marico Industries Ltd.
Consultant: M/s. Jacobs H & G Pvt. Ltd.
|
27.00 |
Completed in time in 4months.
YEAR:2001-02. |
| 08 |
Construction
of Soap Plant, at Goa for
M/s. Hindustan Unilever Ltd.
Consultant: M/s. Kværner Powergas India Ltd.
|
69.51
+
30.00*
|
Completed in time in 8months.
YEAR:2000-01. |