| Sr. No. |
Name of the Project and Location
|
Project
Cost
(INR Million)
|
Remark |
| 01 |
Construction of Heat Treatment Shop & MCD-II Factory Building, Pune for
M/s. Bharat Forge Ltd. |
14.00
+
5.00*
|
Completed in time in 4months.
YEAR: 1999-00. |
Construction of Factory Complex at MIDC Ranjangaon, Pune for
M/s. Kalyani Carpenter Special Steels Ltd. |
13.50
+
7.00*
|
Completed in time in 3months.
YEAR: 1999-00. |
| 02 |
Construction of Iron foundry Project building at Goa for
M/s. Teksid Kalyani Iron Foundry Ltd.
Consultant: M/s. Dalal Consultant and Engineers Ltd. |
143.00
|
Completed in time in 14.5months.
YEAR: 1998-99. |
| 03 |
Construction of Industrial Shed and Administrative Building at Chakan for
M/s. Bajaj Electricals Ltd.
Consultant: M/s. Dongre and Dongre Associates. |
25.00 |
Completed in time in 5months.
YEAR: 1997-98. |
| 04 |
Construction of Industrial Building at Urse, Pune for
M/s. DGP Hinoday Industries Ltd
Consultant: Mr. Chaugule Sant and Associates. |
47.50
|
Completed before time in 9 months with early completion bonus.
YEAR: 1997-98. |
| 05 |
Construction of Industrial Sheds at Urse, Pune for
M/s. Jaya Hind Industries Ltd.
Architectt:.M/s. S.B.Thorat and Partners. |
55.00 |
Completed in time in 10 months.
YEAR: 1995-96. |