Sr.
No. |
Name of the Project
and Location
|
Project Cost
(INR Million)
|
Remark |
| 01 |
Civil and Structural work of Everest Phase – 2 Plant at Baddi, Himachal Pradesh for
M/s. Cadbury India Ltd.
Consultant: M/s. Kværner Powergas India Pvt. Ltd.
|
60.00
+
25.00*
|
Completed in time in 6 months.
YEAR: 2006-07.
|
| 02 |
Expansion of Existing Factory Building at Ponda, Goa for
M/s. Nestlé India Ltd.
Consultant: M/s. Semac Pvt Ltd.
|
13.50
|
Completed in time in 3.5 months.
YEAR: 2001-02.
|
| 03 |
Construction of beverage bottling plant at Jaipur for
M/s. Lend Lease Projects Pvt. Ltd.
Consultant: M/s. Semac Pvt Ltd.
|
65.00
|
Completed before time in 6 months with early completion bonus.
YEAR: 1999-00.
|
| 04 |
Construction of beverage bottling plant at
a. Delhi (Ghaziabad)
b. Goa
c. Bangalore
d. Vijayawada, for
M/s. Lend Lease Projects Pvt Ltd.
Consultant: M/s. Y. S. Sane Associates
|
400.00
|
Completed before time in 8 months with early completion bonus.
YEAR: 1998-99.
|
| 05 |
Construction of beverage bottling plant at Hyderabad for
M/s. Lend Lease Projects Pvt. Ltd.
Consultant: M/s. Humphreys and Glasgow Consultants Ltd.
|
15.00
|
Completed before schedule in 2 months with early completion bonus.
YEAR: 1997-98.
|
| 06 |
Construction of beverage bottling plant at Bangalore for
M/s. PepsiCo India Holdings Pvt. Ltd.
Consultant: M/s. Chemtex Engineering of India Ltd.
|
40.00
|
Completed before schedule in 5 months with early completion bonus.
YEAR: 1997-98.
|